1 (800) 971-1124
Error
  • JLIB_APPLICATION_ERROR_COMPONENT_NOT_LOADING
  • JLIB_APPLICATION_ERROR_COMPONENT_NOT_LOADING

Gleason Library Electricity

Overview

Using hourly kWh values for Gleason Library from December 2014 through early January 2016, we show the energy consumption of various electrical assets at the Gleason Library. We group the 73 circuits named in the SiteSage EMS into Lighting, Pumps, RTU and Miscellaneous in an effort to separate the energy usage into logical groups so that it might be easier to evaluate where future conservation measures can best be applied.

For calendar year 2015, we calculate the Library used 133,013 kWh of electric energy. The six weather-intense months of Jan, Feb, Mar, Jul, Aug, and Sep accounted for 60% of the total. There were 7,790 heating degree-days and 681 cooling degree-days in 2015 (using a 65°F base). If the nominal conditioned space of the Library is 11,000 sq. ft., then the electric energy consumed translates to 12.1 kWh/sf/year, which in turn translates to an Energy Use Intensity (EUI) contribution of 41.3 kBtu/sf/year. This would be an excellent EUI if electricity were the only fuel in use at the Library. We would prefer to make the better calculation by including the use of other fuels if the Town could make the utility bills available to us.

We take a specific look at Peak Demands during the period to better understand what mitigation techniques might be deployed to minimize utility demand charges. We calculate that if no mitigation takes place, and if Eversource makes good on the promise to double demand charges next year, the effect will as high as $5,600 in 2016 depending on when the rate hike takes place.

Town of Carlisle, Gleason Library

Monthly kWh electricity by circuit, through .

Circuit
Average Cost, $/month
MonthkWhCost
+ Show Data Table

Weather Regression

There is insufficent data to do regression on weather at the monthly HDD/CDD level. A possible analysis would use HDD/CDD on daily or hourly kWh and even to filter the data for occupancy, but this analysis was out of scope for now. We did take a quick approach to show some interesting correlations. Expand the "Show Data Table" section above, and note that the rightmost two columns show R2 for monthly kWh on HDD and CDD. In this quick approach, we make up for the lack of data by defining the heating periods as three winter months (Dec, Jan, Feb) plus all six shoulder months (Mar, Apr, May, Sep, Oct and Nov). Similarly, for CDD we use all shoulder months plus the three cooling season months (Jun, Jul, Aug). We took this approach because the shoulder months in many cases show significant HDD and/or CDD as shown in the first two rows of the table.

Using the data table above, we note high correlations (highlighted in red) on certain circuits, which in most cases are fairly obvious:

  • Lighting Panel 31 correlates very closely with HDD. While we normally don't expect lighting to correlate with weather, the shorter daylight hours during the winter months can have a "weather" effect on lighting. Without specific knowledge of the equipment on LP 31, we cannot conclude anything except that there is an apparent correlation.
  • Pump #1 correlates well with HDD, and Pump #2 correlates fairly well with CDD. This is proabably obvious if Pump #1 is related to a heating loop and Pump #2 is related to cooling.
  • Smaller circuits also show correlation to HDD, such as Men's Room Heat, Back Stairwell and the Mechanical Room. It's worth casually noting the apparent correlation of the Elevator to CDD. Without knowing the demographics of occupancy in the cooling season, it would be a stretch to conclude anything but it does seem like people might be more likely to use the elevator during warm weather.
  • The notable expected correlations are the Cooling Tower and RTU with CDD. We will discuss this further below, because the coincident operation of these two assets drive the peak demands during the summer.

The above statements may be far more conclusive than the data permits, but we do think that several weather-dependent relationships certainly exist.

Peak Demand


Notice: Undefined variable: mysql_host in /home/aeintel/public_html/appdev/includes/inc_connect.php on line 17

Notice: Undefined variable: mysql_user in /home/aeintel/public_html/appdev/includes/inc_connect.php on line 17

Notice: Undefined variable: mysql_password in /home/aeintel/public_html/appdev/includes/inc_connect.php on line 17

Warning: mysql_connect(): Access denied for user ''@'localhost' (using password: NO) in /home/aeintel/public_html/appdev/includes/inc_connect.php on line 17
Could not connect : Access denied for user ''@'localhost' (using password: NO)
Discussion

In the visualization above, we take the hourly kWh values and sort them ascending from low to high (left to right). The chart can be dynamically filtered by clicking on the circles in the legend. When the chart is first loaded, we see that the base load for the Library is approximately 4.8 kW, signified by the left edge of the data where all values are at or above 4.8. In other words, when the Library is in its most shutdown state, it still demands 4.8 kW.

At the right edge of the data, we see that in 5% of the hours during the period, the demand was 28.2 kW or higher. The area under that data amounts to 10.3% of the total energy; when the Library is running at full tilt, it consumes about twice the energy of its average. In terms of peak demand mitigation, the hours at the most extreme right edge of the chart are of most interest. Those are the hours that the utility will use to calculate the peak demand charge on each month's bill.

We know that Gleason for all intents operates on a six-day schedule. If we click on "wd", all weekday lines are removed, leaving only weekend data. We see that the curve holds it's approximate shape, but the average of the data drops to 12.3 kWh (per hour). When we click on "sat" to remove the Saturday data points, we see that the shape changes dramatically - only Sunday data remains, and we see the average drops dramatically to just 10.5 kWh/hr.

A better version of this visualization would allow filtering for months, seasons and a true occupancy schedule. Over time, as AEI collects more long-term data, another enhancement could be year/year and season/season comparisons.

Monthly Peak Hours Identified

Using our analysis of the SiteSage data, after correcting for a flaw in their API that calculates kW, we have identified the peak demand period in each of the months where we have data. We use these peak hours to make a proxy calculation of the Gleason electric utility bill, and do a quick assessment of the effect of demand charge increases forecast for 2016. Finally, we show the underlying components of the equipment in use that is driving the peak usage, and with this we may be able to schedule equipment in a way that minimizes the peak demands.

We used the rates in effect on the December 2014 NSTAR bill for the Library.

          Distribution Charges Energy Charges        
Period Peak Demand Date/Time Period Max 15' kW Period kWh Over 10kW DC (Dist) DC (Trans) D+T EC, 1st 2000kWh D+T EC, Next 4800kWh D+T EC, Over 6800kWh 2015 Demand/Total Total Est Bill Demand Charges 2x Demand Charges 4x
Rates, Dec 2014 9.43 7.04 0.02653 0.02148 0.01961
Dec-14 2014-12-09 12:00 Tue 32.67 11,059.97 22.67 $213.81 $159.62 47.62 90.05 71.95 64.0% $583.04 956.47 1,703.32
Temp, 34°F
Humidity, 100%
Top CircuitskW
3860.279855.kW:LP 226.26
3860.279852.kW:LP 315.05
3860.279796.kW:Pump #14.45
3860.279846.kW:LP 213.15
3860.279808.kW:Vestibule Heat1.66
3860.279843.kW:LP121.26
 
Jan-15 2015-01-17 11:15 Sat 35.21 13,595.17 25.21 $237.77 $177.51 47.62 90.05 114.77 62.2% $667.71 1,082.99 1,913.54
Temp, 14°F
Humidity, 34%
Top CircuitskW
3860.279855.kW:LP 225.81
3860.279852.kW:LP 314.86
3860.279846.kW:LP 213.13
3860.279796.kW:Pump #13.09
3860.279808.kW:Vestibule Heat3.08
3860.279859.kW:RTU2.18
3860.279843.kW:LP121.12
3860.279825.kW:Vestibule Heat East1.10
3860.279823.kW:Men's Room Heat1.01
 
Feb-15 2015-02-14 10:00 Sat 33.46 13,122.37 23.46 $221.27 $165.19 47.62 90.05 106.78 61.3% $630.92 1,017.38 1,790.30
Temp, 10°F
Humidity, 51%
Top CircuitskW
3860.279852.kW:LP 315.51
3860.279855.kW:LP 225.05
3860.279796.kW:Pump #14.38
3860.279846.kW:LP 213.17
3860.279859.kW:RTU2.18
3860.279843.kW:LP121.12
3860.279825.kW:Vestibule Heat East1.07
3860.279823.kW:Men's Room Heat1.05
3860.279808.kW:Vestibule Heat0.95
 
Mar-15 2015-03-07 10:00 Sat 30.60 12,048.07 20.60 $194.30 $145.06 47.62 90.05 88.64 60.0% $565.67 905.03 1,583.75
Temp, 25°F
Humidity, 43%
Top CircuitskW
3860.279855.kW:LP 225.14
3860.279852.kW:LP 315.07
3860.279796.kW:Pump #14.42
3860.279859.kW:RTU2.19
3860.279808.kW:Vestibule Heat2.18
3860.279846.kW:LP 211.77
3860.279843.kW:LP121.54
 
Apr-15 2015-04-09 10:00 Thu 28.48 8,715.17 18.48 $174.29 $130.12 47.62 90.05 32.35 64.2% $474.42 778.83 1,387.64
Temp, 34°F
Humidity, 96%
Top CircuitskW
3860.279855.kW:LP 225.63
3860.279796.kW:Pump #14.14
3860.279852.kW:LP 313.84
3860.279846.kW:LP 212.78
3860.279859.kW:RTU2.16
3860.279843.kW:LP121.31
 
May-15 2015-05-07 10:30 Thu 29.26 7,326.61 19.26 $181.66 $135.62 47.62 90.05 8.89 68.4% $463.85 781.14 1,415.71
Temp, 73°F
Humidity, 30%
Top CircuitskW
3860.279859.kW:RTU7.96
3860.279855.kW:LP 225.35
3860.279840.kW:Elevator2.77
3860.279846.kW:LP 212.41
3860.279810.kW:Hot Water Heater1.47
3860.279843.kW:LP121.31
3860.279852.kW:LP 310.98
 
Jun-15 2015-06-16 12:30 Tue 43.68 9,913.50 33.68 $317.58 $237.09 47.62 90.05 52.59 74.5% $744.93 1,299.60 2,408.94
Temp, 65°F
Humidity, 84%
Top CircuitskW
3860.279849.kW:Outside AC23.20
3860.279855.kW:LP 226.16
3860.279799.kW:Pump #23.45
3860.279846.kW:LP 212.53
3860.279843.kW:LP121.26
3860.279852.kW:LP 310.88
 
Jul-15 2015-07-30 14:00 Thu 42.38 14,035.13 32.38 $305.32 $227.94 47.62 90.05 122.20 67.2% $793.12 1,326.37 2,392.87
Temp, 88°F
Humidity, 57%
Top CircuitskW
3860.279859.kW:RTU11.43
3860.279849.kW:Outside AC9.11
3860.279855.kW:LP 225.91
3860.279799.kW:Pump #23.46
3860.279846.kW:LP 212.86
3860.279810.kW:Hot Water Heater1.36
3860.279843.kW:LP121.33
 
Aug-15 2015-08-20 12:45 Thu 41.21 14,152.65 31.21 $294.27 $219.69 47.62 90.05 124.19 66.2% $775.81 1,289.77 2,317.68
Temp, 84°F
Humidity, 55%
Top CircuitskW
3860.279859.kW:RTU10.97
3860.279849.kW:Outside AC7.70
3860.279855.kW:LP 226.31
3860.279799.kW:Pump #23.48
3860.279846.kW:LP 212.79
3860.279843.kW:LP121.37
3860.279810.kW:Hot Water Heater1.07
 
Sep-15 2015-09-09 14:15 Wed 40.39 12,610.74 30.39 $286.55 $213.93 47.62 90.05 98.14 68.0% $736.29 1,236.78 2,237.74
Temp, 91°F
Humidity, 36%
Top CircuitskW
3860.279859.kW:RTU11.50
3860.279849.kW:Outside AC6.77
3860.279855.kW:LP 225.84
3860.279799.kW:Pump #23.47
3860.279846.kW:LP 212.77
3860.279843.kW:LP121.38
3860.279810.kW:Hot Water Heater1.37
 
Oct-15 2015-10-02 10:45 Fri 38.39 9,491.03 28.39 $267.73 $199.87 47.62 90.05 45.45 71.9% $650.72 1,118.33 2,053.54
Temp, 51°F
Humidity, 61%
Top CircuitskW
3860.279849.kW:Outside AC16.36
3860.279855.kW:LP 225.86
3860.279799.kW:Pump #23.47
3860.279846.kW:LP 212.75
3860.279859.kW:RTU1.96
3860.279843.kW:LP121.41
 
Nov-15 2015-11-30 16:45 Mon 27.47 8,074.21 17.47 $164.72 $122.97 47.62 90.05 21.52 64.4% $446.88 734.57 1,309.95
Temp, 34°F
Humidity, 67%
Top CircuitskW
3860.279855.kW:LP 226.07
3860.279852.kW:LP 313.92
3860.279846.kW:LP 212.77
3860.279796.kW:Pump #12.69
3860.279843.kW:LP121.32
 
Dec-15 2015-12-28 18:30 Mon 28.13 10,017.95 18.13 $170.98 $127.64 47.62 90.05 54.35 60.9% $490.64 789.26 1,386.51
Temp, 28°F
Humidity, 38%
Top CircuitskW
3860.279855.kW:LP 226.22
3860.279796.kW:Pump #14.07
3860.279852.kW:LP 313.89
3860.279846.kW:LP 212.74
3860.279843.kW:LP121.29
3860.279810.kW:Hot Water Heater0.96
 
Jan-16 2016-01-04 20:00 Mon 29.77 2,562.05 19.77 $186.47 $139.21 47.62 10.54 - 84.8% $383.85 709.54 1,360.91
Temp, 16°F
Humidity, 57%
Top CircuitskW
3860.279855.kW:LP 226.12
3860.279796.kW:Pump #14.41
3860.279852.kW:LP 313.93
3860.279846.kW:LP 212.70
3860.279843.kW:LP121.37
3860.279808.kW:Vestibule Heat1.17
 
 
Toggle all detail above Total Annual Cost $8,407.86 $14,026.04 $25,262.41

The two rightmost columns show the potential impact of a doubling or quadrupling of the utility demand charge. The demand charge averages 60% or more of the average monthly bill, so these charges are significant. In terms of reducing electric energy usage, the focus should be on reducing the peak demands and less so on the average usage.

Click on "show all details above" to see the underlying circuits that most contributed to the peak demands in each period. The tendency is that during winter months, lighting dominates the peak demands. In the cooling season, the peaks are dominated by the RTU and Cooling tower. Lighting Panel 22 is a consistent Top 5 contributor to peak demands. In terms of demand response, we should learn more about the load on LP22 as a potential candidate for reducing the peak demand, as well as lowering the overall average load at the Library. During summer, if the RTU can be decoupled from the Cooling Tower, peak mitigation might also be achievable during those months.

New AEI Energy Maps Just Released

We've just released public versions of our AEI Energy Maps for Los Angeles, San Francisco, New Orleans and others built in partnership with the U.S. DOE Better Communities Alliance.

Visit the AEI Energy Maps page

AEI Featured on Energy Matters 2U Podcast

AEI was recently featured along with Leidos on an Energy Matters 2U Podcast. During the 20 minute conversation, Carl Popolo of AEI and Ron Gillooly, Leidos' Industrial Energy Program Director, discussed how a building's energy data profile combines with a physical audit to target efficiency measures that have specific and verifiable results.

Listen to the Podcast

AEI To Provide Energy Maps to U.S. DOE Better Communities Alliance

AEI is pleased to have been selected as an Affiliate to the U.S. Department of Energy Better Communities® Alliance. AEI is committed to provide its Energy Map solutions to selected partners from a list of 40 noteworthy cities such as Atlanta, Chicago, Denver, Houston, Los Angeles, Miami, New York and San Francisco.

Read More

AEI Selected as MHEC Supplier

June 29, 2017 -- Carlisle, MA -- AEI has been selected as a Massachusetts Higher Education Consortium (MHEC) supplier to provide Facility Maintenance and Energy Assessment Software to MHEC members through June 2020. The letter from MHEC reads: "Your bid response was evaluated and determined to be the most responsible and responsive bid that offered best value to MHEC members".

Read More

Whole-Portfolio Real-Time Main Metering

AEI brings to market a whole-portfolio real-time main meter view of cities, towns and campuses by combining our AEI Soft Start Real-Time technology with our proven Energy Map visualization platform.

For the energy manager who needs to see energy use across the entire building stock in real-time, this affordable solution shadows the utility main meter, requires no BAS integration, feeds upstream applications such as kiosks, and gives the manager real-time insight into demand response opportunities on their own terms. With 1-minute resolution, rolling profiles and SMS and E-Mail alerts, this integrated solution can also help control billing-period peak usage. It's completely incorporated into our Energy Map platform for exploring historical usage, and that means one-stop-shopping for your energy team to study utility trends, track sustainability goals, and to know your real-time position for social awareness and real-time response.

Explore the Demo

The Bigger Apple: City of New York Energy Map

Building on our work last year to deliver an Energy Map of the City of Boston, we figured we should demonstrate a little scalability and bite on something bigger. The result is our City of New York Energy Map that combines data from the PLUTO and LL84 disclosure reporting datasets and shows electricity, natural gas, oil, steam and water consumption for over 13,000 properties with a combined GSF of over 1.8 billion ft2. The data includes GHG emissions, and for most properties we're able to show trends since 2011.

Read More in News

AEI on Twitter

AEI Commissioning

Are your buildings running efficiently? Let's look at the data and prove it to the managers who pay the utility bills. Efficiency problems? Download the AEI Commissioning Services brochure to see how we can help.